The beneficiary
|
Name of the project
|
no
|
|
First: - oil and gas sector
|
|
South Refineries Company
|
implementation of installation works for the first hydrogenation unit compressors
|
1-
|
Middle Refineries Company
|
ENG., manufacturing and equipping a refining unit with a capacity of 10,000 barrels/day in Al-Diwaniyah refinery (the second unit of Al-Diwaniyah refinery)
|
2-
|
Middle Refineries Company
|
supplying and installation of complementary works for the tanks of Al-Diwaniyah refinery
|
3-
|
Middle Refineries Company
|
Installation work and composition the equipment of the second refining unit in the Diwaniyah Refinery
|
4-
|
Middle Refineries Company
|
Designing and supplying of a measuring and calibration for product LPG with spare parts
|
5-
|
Middle Refineries Company
|
implementation of civil works for the gas generator project / m2
|
6-
|
Middle Refineries Company
|
Project for the construction of the administration building in Al Diwaniyah refinery
|
7-
|
Middle Refineries Company
|
Establishment (15) houses in the Samawa refinery
|
8-
|
Middle Refineries Company
|
Establishment of (15) houses in the Diwaniyah refinery
|
9-
|
Middle Refineries Company
|
Supplying and installing valves for the gasoline improvement unit in the Dora refinery
|
10-
|
Middle Refineries Company
|
supplying of valves for the tank protection system for gasoline and naphtha products
|
11-
|
Middle Refineries Company
|
implementation of industrial water treatment unit in Al-Diwaniyah refinery
|
12-
|
Middle Refineries Company
|
implementation of engineering works for the development of Al-Diwaniyah refinery
|
13-
|
Middle Refineries Company
|
implementation of the second station building in Al- Dora refinery
|
14-
|
Middle Refineries Company
|
supply and installation of four tanks a capacity of 5000 m3 to transfer ownership in the Samawa Refinery
|
15-
|
Middle Refineries Company
|
Rehabilitation of light oil towers
|
16-
|
South Refineries Company
|
construction of electrical power stations in the Maysan Refinery
|
17-
|
Middle Refineries Company
|
maintenance grease cooling towers 1.2 in Dora
|
18-
|
South Refineries Company
|
Rehabilitation of crushing unit by catalyst .
|
19-
|
South Refineries Company
|
implementation of a water intake station and buildings for Maysan refinery project
|
20-
|
South Refineries Company
|
Installation of equipment liquid gas unit
|
21-
|
Middle Refineries Company
|
implementation of civil works for the installation of compressors (K403.K401
|
22-
|
South Refineries Company
|
implementation of burial
works in vicinity of the cracking unit by catalyst
|
23-
|
north Refineries Company
|
Rehabilitation of power units for Salah El-Din Refinery 1 and 2
|
24-
|
South Refineries Company
|
Supplying and installing the tanks of the gasoline improvement unit
|
25-
|
|
ministry of oil |
Establishment of the administration building for al - Najaf refinery |
-26 |
|
Second:- electricity sector
|
|
the State Company for Systems
|
hadytha diesel project
|
1-
|
Ministry of Electricity / General Directorate of gas production projects
|
implementation of construction of a water intake for the site of the Al-Quds power station gas project/3
|
2-
|
Ministry of Electricity
|
Implementation links of the Al-Quds Thermal Station
|
3-
|
Ministry of Electricity
|
Implementation of( control building transformer foundations cables lanes) in alqudos thermal station
|
4-
|
Ministry of Electricity/General Directorate of Production power Electricity /middle Region
|
Construction of a Tanks parking yard in Al-Sadr power station gas
|
5-
|
State company of electric power transmission
|
implementation of electrical transfer station / East Rusafa station
|
6-
|
State company of electric power transmission
|
implementation of electrical transfer station / Sabiyat station
|
7-
|
State company of electric power transmission
|
implementation of electrical transfer station / Shaab station
|
8-
|
State company of electric power transmission
|
implementation of electrical transfer station / Shuala station
|
9-
|
State company of electric power transmission
|
implementation of electrical transfer station / Shatra station
|
10
|
State company of electric power transmission
|
implementation of electrical transfer station / Ibrahimiya station
|
11
|
State company of electric power transmission
|
implementation of electrical transfer station / Shomali station
|
12
|
State company of electric power transmission
|
implementation of electricity transfer station / new Samawa station
|
13-
|
General directorate of al- sadder electrical distribution
|
implementation of civil and electrical works for Sabaa Qusour Secondary station
|
14
|
Ministry of Electricity
|
Implementation of civil and electrical works for the secondary presidential power station
|
15-
|
Ministry of Electricity
|
supply of power transformers number of / 13, design and implementation of concrete bases north of Samawah - Nasiriyah Industrial - North Amara - West Basra
|
16-
|
|
Third :- industry sector
|
|
state Company for Construction Industries
|
supplying and construction of readymade concrete plant
|
1-
|
the State Company for Mining Industries and Waterproofing
|
designing, supplying and installing production lines for the expansion project of the asphalt products factory
|
2-
|
Car state company in al -Escandria
|
Contract for casting the floor of the assembly line project (Renault), Alexandria trucks
|
3-
|
state Company for Information Systems
|
implementation of the Data Center building and the addition of the second floor
|
4-
|
Ministry of Industry and Minerals
|
Supply and construction of watchtowers
|
5-
|
The General Authority for Industrial Research and Development
|
Design and implementation works for the building of laboratories of the Research and Development Authority, Al-Razi Center and the building of the Chemical and Petrochemical Research Center with all its technological attachment
|
6-
|
Ministry of Industry and Minerals / general directorate of Industrial Development
|
Implementation of the first phase of the industrial city in Dhi Qar Governorate
|
7-
|
General Directorate of Industrial Development
|
Development of Nahrawan Industrial Complex / the second Phase
|
8-
|
the state Company for Vegetable Oils
|
designing, supplying, manufacturing and installing liquid oil tanks no. 6 in Al-Mamoun, Al-Rasheed and Ali Al-Hadi factories,
|
9-
|
directorate of Industrial Development and Organization
|
designing, supplying, installing and operating an industrial water treatment unit for ink manufacturers (Amreya) industrial resins (Jihad) in Taji,
|
10-
|
State Company of phosphate
|
Rehabilitation of waste network pipes
|
11-
|
Industrial cultural center
|
Rehabilitation of the industrial cultural center
|
12-
|
the State Company for Mining Industries and Waterproofing
|
Supplying, installing and operating a polymeric felt production line in Basra.
|
13-
|
state company of iron and steel
|
Implementation of rehabilitation works for the iron and steel plant,
|
14
|
Ministry of industry and material/Al-Furat State Co.
|
complete the implementation of an integrated modern plant for the production of soda and chlorine with a capacity of 45 tons / day of 100% complete soda with membrane cell technology
|
15
|
|
industrial cities authority |
industrial city in al - anbar / phase one |
16 |
|
Fourth : higher education and scientific research sector
|
|
Al-Nahrain University
|
Establishment of classrooms for Al-Kadhimiya College of Medicine,
|
1-
|
Baghdad
|
Construction of multi-purpose halls
|
2-
|
|
AL-QADISIYAH |
Establishment of multi - purpose classrooms made of steel structures in the college of administration and economics / university of al- Qadisiyah . |
3- |
|
Fifth : ministry of youth and sport
|
|
Basra
|
Construction, installation and operation of a water purification unit for Basra sports city with all attachment with capacity 1000 m3/hour Basra
|
1-
|
Basra
|
Supplying ,laying and implementing of the water conveyor pipe
|
2-
|
Basra
|
Implementation of three sub-gates in the sports city
|
3-
|
Ministry of Youth and Sports
|
supply and implement of external lighting network for the annual roads in the Sports City in Basra
|
4-
|
Ministry of Youth and Sports
|
Supplying and installing a water filtration unit with a capacity of (1200) m3/hour
|
5-
|
Ministry of Youth and Sports
|
Design and construction of 3 concrete water tanks with a capacity of 10,000 m3
|
6-
|
|
sixth:- ministry of construction and housing
|
|
Basra
|
Construction of khaled ibn alwalid bridge
|
1-
|
Basra
|
Re-construction of highway traffic bridge on shatt al-basra
|
2-
|
|
Seventh : ministry of agriculture
|
|
Salah al-den
|
construction of modern villages in the industrial city in al-alam
|
1-
|